Production flow with subcontracting in Open-Prod
- Type
- Work project
- Date
- 16 October 2026
- Status
- completed
- Technologies
- Open-Prod 10, Odoo, MES, QWeb, Lecteur de codes-barres
- Skills
- B1.5 Make an IT service available to users; B1.6 Organise one’s professional development
Context
At 1Life, new consultants train on Open-Prod with demo databases before working with customers. On 16 October 2026, I presented a complete flow in Open-Prod to the whole consulting team, the technical director, the project director and the regional director: from the sale of a manufactured product to its invoice, with one step outsourced to a subcontractor.
To make the flow concrete, a simple example: making and selling a leather bag.
Objectives
- Run a complete production flow in Open-Prod, from sale to invoice.
- Include a subcontracted step: packaging the product.
- Show both ways of declaring production: the form view, and the MES view for tablets, with a barcode scanner.
- Explain each step to consultants and to management.
Implementation
The scenario
A customer orders a bag. To make it, you need leather and buttons, bought from suppliers.
- Bill of materials: the list of the bag's components, the leather and the buttons.
- Routing: the sequence of manufacturing operations, micro-perforation then assembly, before packaging: wrapping the bag, outsourced to a subcontractor.
The flow in Open-Prod
- The sale: the customer's order for the bag.
- The manufacturing order (MO), created as a draft, then confirmed.
- The first work order (WO): confirming it creates a draft purchase order (PO) for the raw materials, the leather and the buttons.
- Buying the raw materials: confirming the purchase order.
- The consumption and production declarations of the first work order.
- The second work order.
- The third work order, subcontracted: it triggers a subcontracting purchase, created as a draft, then confirmed.
- The round trip to the subcontractor: processing the delivery note, which sends the bag to the subcontractor, then the goods receipt when it comes back.
- Finished production: the bag is complete.
- Delivery to the customer: processing the sale's delivery note.
- The invoices: the raw-material supplier's, the subcontractor's and the customer's. The flow is complete.
Production is declared in two ways: in the form view, and in the MES view (for Manufacturing Execution System, the shop-floor tracking system), a simplified view for tablets, used with a barcode scanner. The work order has its own PDF report, laid out with QWeb, with QR codes. The stock movements generated at each step can be seen in Open-Prod.
Results and testing
The flow was run from start to finish in front of the team, from the customer's order to the three invoices: supplier, subcontractor and customer.
Skills applied
- Bill of materials and routing of a manufactured product, with a subcontracted operation
- Following a flow from start to finish in an ERP: sales, purchasing, production, stock and invoicing
- The subcontracting process: subcontracting purchase, delivery notes and goods receipts, subcontractor's invoice
- Shop-floor production declarations: MES view on a tablet and barcode scanner
- Presenting a business process to consultants and management